Parr Richey Frandsen Patterson Kruse

Call 317-269-2500 or Text 317-269-2509

  • Home
  • About
    • Attorney Profiles
    • Firm History
    • Firm News
    • Career Opportunities
      • Attorneys
      • Law Students
      • Professional Staff
    • In the Community
    • Helpful Links
  • Practice Areas
    • Alternative Dispute Resolution
    • Appeals
    • Business Organizations
    • Education
    • Estate Planning & Probate
    • Governmental Affairs
    • Labor & Employment
    • Litigation
    • Policyholder & Insurance Recovery
    • Real Estate & Land Use
    • Utilities Law
  • Personal Injury
  • Blog
  • Contact
  • Payment Portal
    • Pay Invoice
    • Pay Retainer
Parr Richey Frandsen Patterson Kruse

Text Us 317-269-2509

  • Home
  • About
    • Attorney Profiles
    • Firm History
    • Firm News
    • Career Opportunities
      • Attorneys
      • Law Students
      • Professional Staff
    • In the Community
    • Helpful Links
  • Practice Areas
    • Alternative Dispute Resolution
    • Appeals
    • Business Organizations
    • Education
    • Estate Planning & Probate
    • Governmental Affairs
    • Labor & Employment
    • Litigation
    • Policyholder & Insurance Recovery
    • Real Estate & Land Use
    • Utilities Law
  • Personal Injury
  • Blog
  • Contact
  • Payment Portal
    • Pay Invoice
    • Pay Retainer
Email

CALL

Experienced Litigators And Advocates Serving Clients Across Indiana

  1. Home
  2.  ► 
  3. Utility Law
  4.  ► 
  5. INDIANA SUPREME COURT MODIFIES DECISION TO ALLOW RECOVERY OF COST OVERRUNS DURING RATEMAKING CASE

INDIANA SUPREME COURT MODIFIES DECISION TO ALLOW RECOVERY OF COST OVERRUNS DURING RATEMAKING CASE

Parr Richey Frandsen Patterson Kruse LLP | Oct 29, 2018 | Utility Law |

On June 20, 2018, the Indiana Supreme Court upheld a narrow interpretation of the Transmission, Distribution and Storage System Improvement Charge (“TDSIC”) statute in NIPSCO Industrial Group v. Northern Indiana Public Service Co., 100 N.E.3d 234 (Ind. 2018). A summary of that case can be found here: https://www.indianabusinesslawyerblog.com/nipsco-industrial-group-v-northern-indiana-public-service-co-100-n-e-3d-234-ind-2018/.

On September 25, 2018, the Indiana Supreme Court reissued their opinion in response to a rehearing on the issue. The modified opinion is largely identical to the opinion issued in June. The TDSIC statute allows for periodic rate increases to cover 80 percent of the approved cost estimates for an improvement project without going through the traditional ratemaking process. The remaining 20 percent of improvement costs are recovered through the next general rate case filed by the utility with the Indiana Utility Regulatory Commission (“Commission”). The Supreme Court modified the June opinion to add a clause clarifying that any cost overruns incurred during a TDSIC improvement project that are “specifically justified by the utility and specifically approved by the Commission” are also recoverable during the next general rate case filed with the Commission in addition to the remaining 20 percent of improvement costs. 100 N.E. 3d at 244.

 

Jeremy Fetty is a partner in the law firm of Parr Richey with offices in Indianapolis and Lebanon. Mr. Fetty is current Chair of the Firm Utility and Business Section and often advises businesses and utilities (for profit, non-profit and cooperative) on regulatory, compliance, and transactional matters.

The statements contained herein are matters of opinion and general information only and are not to be considered legal advice and should not be construed to form an attorney-client relationship. If you have any questions regarding this article, please contact an attorney.

 

 

Recent Posts

  • Case Summary: Dupont Water Co. v. City of Madison 
  • Indiana Flooding: Understanding Water Damage and Insurance Coverage
  • Indiana Appeals Court Affirms Bad-Faith Claim Against Erie Insurance
  • What If Evidence Is Destroyed In A Lawsuit?
  • The Number Of Remonstrators Controls Opposition To Establishemnt Of A Conservancy District

Archives

Categories

RSS Feed

Subscribe To This Blog’s Feed

Contact Our Office To Learn How We Can Serve You

Parr Richey Frandsen Patterson Kruse

Phone:
317-269-2500

  • Follow
  • Follow
  • Follow
  • Follow

Indianapolis Law Office

251 North Illinois Street
Suite 1800
Indianapolis, IN 46204

Phone: 317-269-2500
Fax: 317-269-2514
Toll Free: 888-337-7766

Lebanon Law Office

225 West Main Street
PO Box 668
Lebanon, IN 46052


Phone:
765-482-0110
Phone: 317-269-2509
Fax: 765-483-3444
Toll Free: 888-532-7766

Chicago Law Office

One East Wacker Drive
Suite 2600
Chicago, IL 60601

Phone: 312-724-8280
Fax: 773-960-8600

Review The Firm
Pay Invoice
Pay Retainer
Schedule Payment

© 2026 Parr Richey Frandsen Patterson Kruse LLP • All Rights Reserved

Disclaimer | Site Map | Privacy Policy | Business Development Solutions by FindLaw