Parr Richey Frandsen Patterson Kruse
Call 317-269-2500 For A Consultation
  • Home
  • About
    • Attorney Profiles
    • Firm History
    • Firm News
    • Career Opportunities
      • Attorneys
      • Law Students
      • Professional Staff
    • Helpful Links
  • Practice Areas
    • Alternative Dispute Resolution
    • Appeals
    • Business Organizations
    • Education
    • Estate Planning & Probate
    • Governmental Affairs
    • Labor & Employment
    • Litigation
    • Policyholder & Insurance Recovery
    • Real Estate & Land Use
    • Utilities Law
  • Personal Injury
  • Blog
  • Contact
  • Payment Portal
    • Pay Invoice
    • Pay Retainer
Parr Richey Frandsen Patterson Kruse
  • Home
  • About
    • Attorney Profiles
    • Firm History
    • Firm News
    • Career Opportunities
      • Attorneys
      • Law Students
      • Professional Staff
    • Helpful Links
  • Practice Areas
    • Alternative Dispute Resolution
    • Appeals
    • Business Organizations
    • Education
    • Estate Planning & Probate
    • Governmental Affairs
    • Labor & Employment
    • Litigation
    • Policyholder & Insurance Recovery
    • Real Estate & Land Use
    • Utilities Law
  • Personal Injury
  • Blog
  • Contact
  • Payment Portal
    • Pay Invoice
    • Pay Retainer
Email

CALL

Experienced Litigators And Advocates Serving Clients Across Indiana

  1. Home
  2.  ► 
  3. Utility Law
  4.  ► 
  5. Indiana Utility Law – Ind. Office of Utility Consumer Counselor v. Duke Energy Indiana, LLC, 21A-EX-2702 (Ind. Ct. App. 2023)

Indiana Utility Law – Ind. Office of Utility Consumer Counselor v. Duke Energy Indiana, LLC, 21A-EX-2702 (Ind. Ct. App. 2023)

Parr Richey Frandsen Patterson Kruse LLP | Jul 10, 2023 | Utility Law |

On February 21, 2023, the Indiana Court of Appeals reversed an Indiana Utility Regulatory Commission (“Commission”) order granting Duke Energy Indiana (“Duke”) recovery of costs pursuant to federal Environmental Protection Agency (“EPA”) rules for treating coal ash and remediating ash ponds because the Commission had not yet approved the project, which constituted impermissible retroactive ratemaking. The central issue before the court was whether the Commission’s order allowing Duke to recover costs incurred “before or during the pendency of the proceeding, [and] prior to the issuance of the [o]rder” violated the prohibition against retroactive ratemaking. Ind. Office of Utility Consumer Counselor v. Duke Energy Indiana, LLC, 21A-EX-2702 at 2 (Ind. Ct. App. 2023) (“Duke Energy”). The Commission’s order grating cost recovery was pursuant to Indiana’s Federal Mandate Statute, which permits utilities, subject to Commission approval, to “track and cover 80% of such federally mandated costs via periodic rate adjustments, with recovery of the remaining 20% deferred to the utility’s next general rate case.” Duke Energy, 21A-EX-2702 at 11. The court determined that this was a question of law because the focus of the challenge was “whether the Commission can approve the reimbursement of already incurred costs without violating the perceived prospective language of the Federal Mandate Statute.” Id. at 7-8.

The “perceived prospective language” was recognized by the Indiana Supreme Court in Duke’s traditional rate case, Ind. Off. Of Util. Consumer Couns. V. Duke Energy Ind. LLC., 183 N.E.3d 266 (Ind. 2022) (“DEI”), where it noted that the Federal Mandate Statute “is framed in the future tense and speaks of ‘projected’ costs for ‘proposed’ projects which would seem to require [C]omission approval before a utility incurs the cost.” DEI, 183 N.E.3d at 270 (internal citations omitted). While agreeing with Duke that the above language was ditca, the court viewed it as “an indication that our supreme court believes a utility can only recoup certain expenses incurred under the Statute after gaining authorization from the Commission to track the expenses.” Duke Energy, 21A-EX-2702 at 14. According to the court, this position “is grounded in the principle that ratemaking is prospective in nature, not retroactive, with the demarcation between retroactive and prospective costs being the date of the Commission’s order, not the filing date of the utility’s petition.” Id. at 9 (internal citations omitted). As such, because the Federal Mandate Statue does not specifically authorize the recovery costs prior to a utility receiving a certificate of public convenience and necessity (“CPCN”), id., permitting recovery of costs “incurred prior to the Commission’s authorization would undo the purpose of Commission oversight and would present a disservice to the utility’s customers.” Id. at 17.

Therefore, because the Federal Mandate Statute serves as an exception to the general prohibition against retroactive ratemaking and is only effective after a utility receive a CPCN from the Commission for the project, permitting Duke to recover costs it had incurred prior to the Commission’s order “failed to follow the prospective strictures of the Federal Mandate Statute,” requiring reversal. Id.

 

Jeremy Fetty is a partner in the law firm of Parr Richey Frandsen Patterson Kruse with offices in Lebanon and Indianapolis. He often advises businesses and utilities (for profit, non-profit and cooperative) on organizational, human resources, and transactional matters and drafts and reviews commercial contracts.

The statements contained herein are matters of opinion and general information only and are not to be considered legal advice and should not be construed to form an attorney-client relationship. If you have any questions regarding this article, please contact an attorney.

Recent Posts

  • Indiana Appeals Court Affirms Bad-Faith Claim Against Erie Insurance
  • What If Evidence Is Destroyed In A Lawsuit?
  • The Number Of Remonstrators Controls Opposition To Establishemnt Of A Conservancy District
  • Local Government Need Not Provide Health Insurance to Elected Official
  • FERC Legal – Blog Post: Duke Energy Corp. v. FERC, 2018 U.S. App. LEXIS 16108

Archives

Categories

RSS Feed

Subscribe To This Blog’s Feed

Contact Our Office To Learn How We Can Serve You

Parr Richey Frandsen Patterson Kruse

Phone:
317-269-2500

  • Follow
  • Follow
  • Follow
  • Follow

Indianapolis Law Office

251 North Illinois Street
Suite 1800
Indianapolis, IN 46204

Phone: 317-269-2500
Fax: 317-269-2514
Toll Free: 888-337-7766

Lebanon Law Office

225 West Main Street
PO Box 668
Lebanon, IN 46052


Phone:
765-482-0110
Phone: 317-269-2509
Fax: 765-483-3444
Toll Free: 888-532-7766

Chicago Law Office

One East Wacker Drive
Suite 2600
Chicago, IL 60601

Phone: 312-724-8280
Fax: 773-960-8600

Review The Firm
Pay Invoice
Pay Retainer
Schedule Payment

© 2026 Parr Richey Frandsen Patterson Kruse LLP • All Rights Reserved

Disclaimer | Site Map | Privacy Policy | Business Development Solutions by FindLaw